What Next

Carnegie`s Way Update - August 2026


Background
The business case, concept design and preferred route for Carnegie’s Way were approved by Places for Everyone (now the Walk, Wheel, Cycle Trust) in late 2024.  Responsibility for delivering the project was subsequently formally transferred to Fife Council (FC), where it now forms part of the Council’s Active Travel Strategy.

Although Fife Council assumed responsibility for the project in 2024, regrettably, little progress was made until earlier this year.  Changes within FC’s Active Travel Team have, however, brought renewed momentum to the project.

Recent Developments
Unfortunately, the two routes recommended by FC’s consultants have proved unacceptable to the landowner.  Attention has therefore turned to the only alternative route that the landowner has indicated may be acceptable.  This route is shown in blue on the diagram below.

While we welcome the landowner’s willingness to continue discussions, the blue route presents a number of significant challenges.  In particular, the steep gradients at Crossford and through Urquhart Cut will make the route difficult for wheeled users and those with limited mobility.

The route is also constrained at both ends.  At the Crossford end, it would have to connect with a narrow footpath alongside rising ground. At the Dunfermline end, it would be squeezed onto a narrow pavement between a busy road and tenement buildings.  There is also a significant pinch point, together with access to an industrial estate, beside the cottages on the north side of the road.

The Way Forward
Despite these challenges, and with the consent of the landowner, Fife Council is continuing to progress the project.  Detailed ground investigations are now being undertaken based on a high-level concept design, together with an approximate calculation of the land required, both of which were completed in May 2026.  The ground investigations will provide the information needed to develop a detailed design, which is expected to be completed in early 2027.

We remain hopeful that this work will address the outstanding issues, secure the landowner’s approval and allow Carnegie’s Way to finally become a reality.  After such a long period of delay, we hope the project can now move forward towards completion sooner rather than later.